Florida condo owners face up to $320,000 assessments as costs soar

Florida condo owners face up to $320,000 assessments as costs soar
Image Credit: CBS News Miami

Residents of an oceanfront condominium in Fort Lauderdale say a repair project that began as a relatively modest concrete restoration has spiraled into a $36 million overhaul, leaving some owners facing assessments as high as $320,000 while construction drags into its fifth year.

CBS News Miami reporter Joan Murray investigated complaints from residents at the Galleon condominium on Galt Ocean Mile, where owners said they had become frustrated not only with the rising cost of the work but also with delays, quality concerns and turmoil inside the building’s board.

What began as a $1.6 million project has grown more than twentyfold, according to Murray’s report, with individual owners now being assessed between $135,000 and $320,000.

For people who bought into the building expecting ordinary maintenance costs, those figures are difficult to absorb, especially when the work has stretched on for years.

Residents Say The Work Has Taken Too Long

Murray spoke with Sergio Cella, a pilot and mechanical engineer who has lived at the Galleon for about 30 years.

Cella said his 14th-floor balcony had been redone three times because of cracking, and he did not hide his frustration with the workmanship.

“The quality is not there,” he said. “It’s not questionable. It’s despicable.”

Residents Say The Work Has Taken Too Long
Image Credit: CBS News Miami

The condition of the building shown in the report added to residents’ concerns.

Walkways remained under repair, railings were covered with plywood and mesh, and the pool and patio area had been reduced to a concrete platform.

Construction had been underway for nearly five years.

One resident told Murray he expected to be out close to $245,000 personally by the time the project was finished.

That kind of cost would be difficult for many households to absorb even once, let alone alongside years of disruption and uncertainty over when the work will finally end.

Contractor Says The Scope Expanded

Murray also contacted Hartzell, the contractor on the project.

An executive told CBS News Miami in a written statement that the original agreement had covered only a limited amount of structural restoration.

According to the company, the association later chose to significantly expand the project through numerous owner-approved change orders and additional contracts.

Contractor Says The Scope Expanded
Image Credit: CBS News Miami

That explanation helps account for how a $1.6 million job became a $36 million overhaul, but it does not erase the frustration felt by residents who say they were not prepared for the final price.

Large construction projects can become more expensive as hidden problems are discovered, but once costs begin multiplying on this scale, the question becomes whether owners were given enough information along the way to understand what they were agreeing to.

That is especially important in a condominium, where individual residents can end up responsible for enormous assessments tied to decisions made collectively.

Former Board Member Says Costs “Snowballed”

Edward Rumin, an attorney and former member of the Galleon board, told Murray that residents understood repairs were necessary and initially accepted the financial burden.

He said the problem came when the project kept growing.

“Nobody likes assessments,” Rumin said. “We didn’t like the numbers, but we went along with them. Until things got out of control and snowballed.”

Former Board Member Says Costs “Snowballed”
Image Credit: CBS News Miami

He also accused the process of becoming increasingly difficult for owners to follow.

“We were run roughshod over, not told things, and lied to,” he said.

The building’s board has gone through recalls, lawsuits and resignations during the renovation, according to the report.

That kind of leadership instability can make an already complicated construction project even harder to manage, especially when owners are being asked to approve major spending while trust in the board is falling.

Board President Dismisses Residents’ Complaints

Murray tried to speak directly with the Galleon’s board president about the complaints.

When she reached him by phone, he dismissed the concerns.

“You are being had,” he told her. “These are people who can’t afford to live on the ocean.”

He then ended the call.

That response is unlikely to reassure owners who are facing six-figure assessments.

Affordability is obviously part of the problem, but describing residents’ concerns as simply an inability to afford oceanfront living does not address their questions about cost overruns, delays or repeated repairs.

Murray reported that the board president later sold his unit and resigned.

That leaves the building entering yet another phase of leadership change while the renovation remains unfinished.

Florida Condo Repairs Have Become A Much Larger Issue

The Galleon’s situation is part of a broader pattern across Florida.

Murray noted that large-scale condominium restoration projects have become far more common since the 2021 collapse of Champlain Towers South in Surfside, which killed 98 people.

The disaster led to tighter state safety rules and reserve funding requirements aimed at preventing buildings from deferring critical maintenance for too long.

Florida Condo Repairs Have Become A Much Larger Issue
Image Credit: CBS News Miami

Those changes were meant to improve safety, but they have also forced many condo associations to confront repair bills that had been postponed for years.

For owners, that can mean sudden assessments reaching well into six figures.

The Galleon case is especially dramatic because the cost increase was so large, but the broader tension is familiar across Florida: aging buildings need expensive structural work, while residents may not have the cash reserves to absorb the cost.

Owners Say They Do Not Expect The Money Back

Rumin told Murray that residents now feel trapped in the aftermath of the project.

“We are in a morass,” he said. “I don’t think we’ll ever get any of the money back.”

That may be the most telling comment in the report.

For owners, the issue is no longer simply whether the repairs should have been done.

It is whether the project was managed in a way that gave residents confidence that the money was being spent efficiently and the work was being completed properly.

The Galleon remains unfinished, the board has changed again and some residents are still looking at assessments approaching the cost of a house in other parts of the country.

The repairs may be necessary, but the financial burden has become so severe that the project itself is now reshaping what it means to own a condo in the building.

For many residents, the problem is no longer just construction.

It is whether they can afford to stay long enough to see it completed.